EThOS Project
Communications Plan
|
Version |
Date |
Author |
Summary of Changes |
|
0.1 |
02-06-2005 |
Scott Hanley |
|
|
0.2 |
28-09-2005 |
Scott Hanley |
|
|
|
Name |
Title |
Signature |
Date |
|
Prepared by |
Scott Hanley |
Project Manager |
|
02-06-2005 |
|
Reviewed by |
Chris Bailey Colin Galloway |
Project Executive Project Assurance |
|
10-06-2005 |
|
Approved by |
Chris Bailey |
Project Executive |
|
10-06-2005 |
1 Purpose of Document................................................................................................. 3
2 Storage and Organisation of Information and
Documentation........................ 3
3 General
Communication Responsibilities............................................................. 3
4 Stakeholders................................................................................................................. 4
This
section documents the information requirements of all project stakeholders and
the Project Manager and Team members.
Examples of stakeholders are:
The
Project Board, Programme or Portfolio Management, customers and other interested
parties.
|
Stakeholders |
Information
Requirements |
Method and Frequency |
Information
Provider |
Feedback Channel |
|
Programme
Management |
Project
Progress, Project issues, risks and deviations in cost and/or time that may
affect the Programme, |
1. Report in July 2005 and at the end of the Project (June 2006). 2. Informally by email and telephone |
Project
Executive/Board Prepared by
Project Manager |
1. Informally by email and telephone. 2.
Formally by meeting |
|
Project
Board |
Programme
progress, Programme projects progress that influence the Project |
1. Meetings 2. Informally by email and telephone |
Programme
Manager |
1. Informally by email and telephone. 2. Formally by meeting |
|
Project
Board |
Project
Progress, risks and issues that affect the Project. |
1.
Highlight Report
document for every board meeting (see below) 2.
Project Board meeting
every quarter (May 20th 2005, October, January 2006, April, June
project end) 3.
Meeting with Project
Executive fortnightly. 4.
Informally by Ad Hoc
email. 5.
Project Plan 6.
Risk Log 7.
Issue Log 8.
Project Web site |
Project
Manager |
1. Informally by email and telephone. 2. Formally by minuted Project Board meeting |
|
Project
Board |
Forecast
Deviations in cost and/or time out with agreed tolerances |
1.
Exception Report 2.
Informally by email |
Project
Manager |
1.
Informally by email
and telephone. 2.
Formally by minuted
Project Board meeting |
|
Project
Manager |
External
factors within or out with the Programme that may influence the Project. |
1.
Meeting with Project
Executive fortnightly 2.
Email |
Project
Board (executive) |
1.
Informally by email
and telephone. 2.
Formally by minuted
Project Board meeting |
|
Project
Manager |
Work package
progress, risks and issues that may affect the Project. |
1.
Checkpoint Report document at the end of each calendar
month. 2.
WP Leader meeting - May 18th 2005, end of August
2005, 3.
Schedule of site
visits 4.
Informally by Ad Hoc
email 5.
WP Team plan |
Team Leader |
1.
Informally by email
and telephone. 2.
Formally by minuted WP Leader meeting |
|
Team
Leaders, Project Manager |
What is
required to be delivered from their Work Package |
Work package
document. And Team Plan to be agreed and completed by the Project Manager and
the WP Leader |
Team Leader,
Project Manager |
1.
Individual WP minuted
Leader/PM meetings. 2.
Informally by email
and telephone. |
|
Team Leaders |
Task
progress, risks and issues that may affect the Work Package. |
1.
WP Team meeting at
least fortnightly. 2.
Emails 3.
WP Team plan |
Team member |
1. Meeting 2. Emails |
|
All |
Roles and
responsibilities within the project |
1. Project Organisation Document distributed on agreement and completion 2.
Project Web SIte |
Project
Manager |
1.
Informally by email
and telephone. 2.
Formally by minuted
Project Board and WP Leader meetings |
|
All |
Products to
be delivered, tasks to be achieved, by who, by when and how within the Project. |
1. Project Plan distributed once first draft completed and base-lined, thereafter, as and when requested and at WP Leader and Board meetings. 2.
Project Web Site |
Project
Manager |
1.
Informally by email
and telephone. 2.
Formally by minuted
Project Board and WP Leader meetings |
|
All |
How
information is to be communicated through out the Project |
1. Project Communications Plan distributed on agreement and completion 2.
Project Web Site |
Project
Manager |
1.
Informally by email
and telephone. 2.
Formally by minuted
Project Board and WP Leader meetings |
|
All |
Action
points and agreements during meetings |
1. Meeting minutes document 2.
Project Web Site |
Project
Manager |
1.
Informally by email
and telephone. 2.
Formally by minuted
Project Board and WP Leader meetings |
|
All |
Meeting
agendas |
1. Meeting agenda document 2.
Project Web Site |
Project
Manager |
1.
Informally by email
and telephone. 2.
Formally by minuted
Project Board and WP Leader meetings |
|
All |
Meeting
arrangements, times, etc |
By email and
telephone. |
Project
Assurance |
1.
Informally by email
and telephone. |