EThOS Project

 

 

 

 

Communications Plan

 

 

 

 

 

Document History

Version

Date

Author

Summary of Changes

0.1

02-06-2005

Scott Hanley

 

0.2

28-09-2005

Scott Hanley

  1. Official web site address of ethos.ac.uk now live as at 28/09/2005 & reflected in section 2.

 

 

Authorisation

 

Name

Title

Signature

Date

Prepared by

Scott Hanley

Project Manager

 

02-06-2005

Reviewed by

Chris Bailey

 

 

Colin Galloway

Project Executive

 

Project Assurance

 

10-06-2005

Approved by

Chris Bailey

 

Project Executive

 

10-06-2005

 


CONTENTS

1     Purpose of Document................................................................................................. 3

2     Storage and Organisation of Information and Documentation........................ 3

3     General Communication Responsibilities............................................................. 3

4     Stakeholders................................................................................................................. 4


 

1          Purpose of Document

 

2          Storage and Organisation of Information and Documentation

 

3          General Communication Responsibilities

 


4          Stakeholders

This section documents the information requirements of all project stakeholders and the Project Manager and Team members.  Examples of stakeholders are:

The Project Board, Programme or Portfolio Management, customers and other interested parties.

 

Stakeholders

Information Requirements

Method and Frequency

Information Provider

Feedback Channel

Programme Management

Project Progress, Project issues, risks and deviations in cost and/or time that may affect the Programme,

1.       Report in July 2005 and at the end of the Project (June 2006).

2.       Informally by email and telephone

Project Executive/Board

Prepared by Project Manager

1.       Informally by email and telephone.

2.       Formally by meeting

Project Board

Programme progress, Programme projects progress that influence the Project

1.       Meetings

2.       Informally by email and telephone

Programme Manager

1.       Informally by email and telephone.

2.       Formally by meeting

Project Board

Project Progress, risks and issues that affect the Project.

1.       Highlight Report document for every board meeting (see below)

2.       Project Board meeting every quarter (May 20th 2005, October, January 2006, April, June – project end)

3.       Meeting with Project Executive fortnightly.

4.       Informally by Ad Hoc email.

5.       Project Plan

6.       Risk Log

7.       Issue Log

8.       Project Web site

Project Manager

1.       Informally by email and telephone.

2.       Formally by minuted Project Board meeting

Project Board

Forecast Deviations in cost and/or time out with agreed tolerances

1.       Exception Report

2.       Informally by email

Project Manager

1.       Informally by email and telephone.

2.       Formally by minuted Project Board meeting

Project Manager

External factors within or out with the Programme that may influence the Project.

1.       Meeting with Project Executive fortnightly

2.       Email

Project Board (executive)

1.       Informally by email and telephone.

2.       Formally by minuted Project Board meeting

Project Manager

Work package progress, risks and issues that may affect the Project.

1.       Checkpoint Report  document at the end of each calendar month.

2.       WP Leader meeting  - May 18th 2005, end of August 2005,

3.       Schedule of site visits

4.       Informally by Ad Hoc email

5.       WP Team plan

Team Leader

1.       Informally by email and telephone.

2.        Formally by minuted WP Leader  meeting

Team Leaders, Project Manager

What is required to be delivered from their Work Package

Work package document. And Team Plan to be agreed and completed by the Project Manager and the WP Leader

Team Leader, Project Manager

1.       Individual WP minuted Leader/PM meetings.

2.       Informally by email and telephone.

Team Leaders

Task progress, risks and issues that may affect the Work Package.

1.       WP Team meeting at least fortnightly.

2.       Emails

3.       WP Team plan

Team member

1.       Meeting

2.       Emails

All

Roles and responsibilities within the project

1.       Project Organisation Document – distributed on agreement and completion

2.       Project Web SIte

 

Project Manager

1.       Informally by email and telephone.

2.       Formally by minuted Project Board and WP Leader meetings

All

Products to be delivered, tasks to be achieved, by who, by when and how  within the Project.

1.       Project Plan – distributed once first draft completed and base-lined, thereafter, as and when requested and at WP Leader and Board meetings.

2.       Project Web Site

Project Manager

1.       Informally by email and telephone.

2.       Formally by minuted Project Board and WP Leader meetings

All

How information is to be communicated through out the Project

1.       Project Communications Plan– distributed on agreement and completion

2.       Project Web Site

Project Manager

1.       Informally by email and telephone.

2.       Formally by minuted Project Board and WP Leader meetings

All

Action points and agreements during meetings

1.       Meeting minutes document

2.       Project Web Site

Project Manager

1.       Informally by email and telephone.

2.       Formally by minuted Project Board and WP Leader meetings

All

Meeting agendas

1.       Meeting agenda document

2.       Project Web Site

Project Manager

1.       Informally by email and telephone.

2.       Formally by minuted Project Board and WP Leader meetings

All

Meeting arrangements, times, etc

By email and telephone.

Project Assurance

1.       Informally by email and telephone.